Към съдържанието
Джи М Инженеринг

Power Line Sag — Measured with a LiDAR Drone, and What the Bulgarian Ordinance No. 3 Requires

With a LiDAR drone we surveyed a section of a medium-voltage overhead line — 5 poles and 15 conductors. We show how the sag of each conductor and its clearance to the ground and to objects under the line are calculated from the point cloud, and what Ordinance No. 3 requires.

Sag is the vertical distance between the straight line through the two attachment points and the lowest point of the conductor in the span. More important for safety is clearance — how high above the ground, the road or the building the conductor passes at its lowest point. With a LiDAR drone we measure both for every conductor separately, without switching the line off and without climbing the poles.

LiDAR drone point cloud of an overhead line — poles and three conductors above the ground
The section in the point cloud: the poles and the three conductors (red) above the ground and the objects under the line.

In short

  • Survey: 4 August 2026, RIEGL miniVUX-3UAV LiDAR sensor on a drone; a flight of about 3 minutes tied to 8 ground control points.
  • Line: medium-voltage overhead line, 5 poles, spans of 56 to 64 m, plus a 40.5 m branch.
  • Conductors: 15 conductors — each described by a catenary, mean deviation of the points 1–2 cm.
  • Sag: from 1.0 to 2.4 m.
  • Ground clearance: minimum 6.69 m; to an object under the line — 2.4 m.

What Ordinance No. 3 requires

In Bulgaria the minimum clearances are set by Ordinance No. 3 of 2004 on electrical installations and power lines. They are checked at maximum sag — at an air temperature of +40 °C or with ice at −5 °C without wind, without accounting for conductor heating by the current (Art. 620(3)).

Minimum vertical clearance of the conductorsup to 20 kV110 kV220 kV400 kV
to the ground — unpopulated area (Art. 620, Table 45)6 m6 m7 m8 m
to the ground — hard-to-reach area5 m5 m6 m7 m
to the ground — inaccessible area3 m3 m4 m5 m
to the ground — populated area (Art. 634, Table 47)7 m7 m8 m9 m
to the carriageway (Art. 672, Table 55)7.6 m7.6 m8.6 m9.0 m
to the rail head, non-electrified railway (Art. 663, Table 54)7.5 m7.5 m8.5 m9.5 m

The ordinance also sets horizontal clearances to buildings from the outer conductors at their maximum deflection — 2 m at 20 kV, 4 m at 110 kV, 6 m at 220 kV and 9 m at 400 kV (Art. 637). Through forests the corridor width is the distance between the outer conductors plus 6 m for trees up to 4 m, and for taller trees plus twice their mean height (Art. 622). Easement zones around lines are in Ordinance No. 16 of 2004 on easements of energy facilities.

Sources (in Bulgarian): the text of Ordinance No. 3 and Ordinance No. 16. The values are for normal operation; for emergency conditions and for 750 kV the ordinance has separate requirements.

Sag and clearance — what exactly is measured

Conductor sag and clearance Two poles with attachment points, a conductor in the shape of a catenary, the chord between the attachment points, the sag f as the largest distance from the chord to the conductor, and the clearance h from the lowest point to the ground. The span is L. chord between attachment points f — sag h — ground clearance L — span h is checked at maximum sag: +40 °C or ice at −5 °C without wind — when the conductor hangs lowest
Sag f is measured from the chord between the attachment points; clearance h from the lowest point of the conductor to the ground.

How we measure it

  1. LiDAR flight. The drone flies over the route; the laser captures the poles, every conductor, the ground and everything under the line — vegetation, buildings, roads.
  2. Conductor extraction. Conductor points are separated from the cloud, and each conductor in each span is separated automatically from its neighbours.
  3. Catenary. A catenary curve is fitted to the points of each conductor — so the sag and the lowest point are determined even where points are sparser.
  4. Clearances. From the curve to the terrain model and to objects under the line we calculate the smallest vertical distance and its position in the span.
  5. Recalculation to maximum sag. The survey is taken at a specific temperature and load. With the conductor data from the operator, the sag is recalculated to +40 °C and to ice load — and only then are the clearances compared with the requirements.
Plan of the overhead line route with numbered poles C1–C5 and a branch
The route in plan: poles C1–C5, the angle pole C3 with the branch to the west and the objects under the line.

Survey results

The profile along the route shows the three conductors in each span, the ground beneath them and the lines 6 and 7 m above the ground. The arrows mark the lowest point of the bottom conductor in each span.

Profile along the power line route — conductors, poles C1–C5, ground and the lines 6 and 7 m above the ground
Profile along the route. Dashed lines are 7 m (populated area) and 6 m (unpopulated area) above the ground.
SpanLengthSag (top / middle / bottom)Minimum ground clearanceTo object under the line
C1–C256.0 m1.52 / 1.35 / 1.46 m7.72 m5.99 m
C2–C362.0 m1.85 / 1.71 / 1.79 m7.21 m4.69 m
C3–C459.0 m1.85 / 1.88 / 2.07 m6.84 m4.46 m
C4–C564.0 m2.09 / 2.40 / 2.12 m6.69 m2.40 m
Branch from C340.5 m1.18 / 1.35 / 1.02 m7.83 m4.47 m

Clearances are for the bottom conductor, which is closest to the ground.

Chart of the minimum ground clearance of the top, middle and bottom conductor in each span against 6 and 7 m
Minimum ground clearance of each conductor, against 6 and 7 m.
Span C4–C5 — laser points, the catenaries of the three conductors, the sag f and the ground clearance h
Span C4–C5 close up. Under the bottom conductor there is an object about 4.3 m tall — the vertical distance to it is 2.4 m.

What the results show

  • Against 6 m (unpopulated area, up to 110 kV) all conductors have a margin — the smallest is 0.69 m.
  • Against 7 m (populated area) the bottom conductor in spans C3–C4 and C4–C5 is below 7 m already at survey conditions.
  • At +40 °C the sag will be larger and the clearances smaller. That is why, with a small margin, a recalculation is made with the conductor data.
  • The object under the line in C4–C5 is only 2.4 m below the bottom conductor — such spots are checked on site together with the network operator.

Which requirement applies — populated, unpopulated or hard-to-reach area, road or railway — is determined for each span separately. The line voltage and conductor type are confirmed by the operator.

What the client receives

ResultFormat
Classified point cloud — ground, poles, conductors, vegetation, buildingsLAS / LAZ
3D model of the conductors (catenaries) and polesDWG / DXF
Table by span: length, sag, clearances, position of the lowest pointXLSX / PDF
Profiles along the route with the regulatory linesPDF / DWG
Objects and vegetation dangerously close to the conductorsSHP / KML, PDF
Report with methodology, accuracy and conclusionsPDF

Frequently asked questions

Does the line have to be switched off?

No. The drone flies at a safe distance above and beside the line and does not touch it. The survey requires no outage and does not interrupt the power supply.

What is the accuracy?

The cloud is tied to ground control points, and the catenary of each conductor is fitted to hundreds of points. In this example the mean deviation of the points from the curves is 1–2 cm.

Why is the measured sag not the final answer?

Sag depends on temperature and load. The ordinance requires clearances at maximum sag (+40 °C or ice), so the measured geometry is recalculated to those conditions using the conductor data.

Can the vegetation under the line be checked?

Yes. The same cloud shows every tree and shrub under and around the conductors — their height and the distance to the nearest conductor. This is how corridor clearing is planned.

Have a line to check?

Send us the route (KML, DWG or a sketch), the voltage and what you need the data for — clearance check, reconstruction design or corridor clearing. We will propose a flight and a timeline. Send an inquiry or see the Drone LiDAR surveying service.

The project at a glance, with photos: Sag and Clearances of a Medium-Voltage Overhead Line — LiDAR Drone. More completed work — in Projects.

Author: GM Engineering

Have a specific case?

Describe it and get a clear answer and quote.

Send inquiry

Need geodetic or cadastral services?

Get a quote within 2 working hours.